Visit our social media channels
We have already seen the future. Learn about CNAO's expansion project

CNAO Expansion Project

WE HAVE ALREADY SEEN THE FUTURE

Discover
Gianluca Vago

Gianluca Vago

President

CNAO's expansion involves the construction of a second building, contiguous and integrated with the existing one. ...

Read more

Work Progress of the Expansion Project

April 2022

Site preparation excavations

November 2022

Jet grouting for soil consolidation

March 2023

Excavation of the area where the second basement will be built

April 2023

Creation of the floor slab of TAE Life Sciences zone and laying of the reinforcement of the floor slab of the Hitachi zone

May 2023

Aerial view of the rooms on the second basement floor and installation of waterproofing in the foundation of the first basement floor

June 2023

Laying prefabricated panels for wall construction in Hitachi area

July 2023

Laying of prefabricated walls in the Hitachi area

September 2023

Elevation of Hitachi area to the first floor

November 2023

Overall view of the expansion with closure of a portion of the Hitachi enclosure

December 2023

Overall view of the expansion, the connecting area between the existing building and the expansion has been completed up to the attic between the ground floor and first floor

January 2024

Overview of the expansion

March 2025

0 giorni

0 ore

0 minuti

0 secondi

April 2022

Site preparation excavations

Preparation of the site where the new building will stand

November 2022

Jet grouting for soil consolidation

Tillage for mechanical soil improvement

March 2023

Excavation of the area where the second basement will be built

View of area where future center will be built to host new facilities from Hitachi and TAE Life Sciences

April 2023

Creation of the floor slab of TAE Life Sciences zone and laying of the reinforcement of the floor slab of the Hitachi zone

Overall view of the workings of the counter floor of the second basement floor.

May 2023

Aerial view of the rooms on the second basement floor and installation of waterproofing in the foundation of the first basement floor

Hitachi gantry room and rebar installation inside the vertical walls on the first basement floor and in the Hitachi treatment room area; precast shored walls in the second basement floor gantry room

June 2023

Laying prefabricated panels for wall construction in Hitachi area

Laying of reinforcement for the construction of the counter-floor slab of the first basement floor; elevation of the prefabricated vertical walls bordering the Hitachi zone; construction of the slab between the basement floor and ground floor of the connection portion between the existing building and the Hitachi zone

July 2023

Laying of prefabricated walls in the Hitachi area

Overall view of the extension. In the Hitachi area, work is concentrated between the ground and first floors, while in the TAE Life Sciences area, work is still in the basement floors

September 2023

Elevation of Hitachi area to the first floor

The Hitachi area is coming to cover: structures are being laid to complete the floors. Aerial view of Hitachi's gantry and treatment room and the room that will host TAE Life Sciences' high-energy beam machine

November 2023

Overall view of the expansion with closure of a portion of the Hitachi enclosure

Work on the roof of the new Hitachi area and at the floor between the ground floor and the first floor in the connecting portion between the existing building and the extension.

December 2023

Overall view of the expansion, the connecting area between the existing building and the expansion has been completed up to the attic between the ground floor and first floor

Closure of the Hitachi cover (the sheet metal cover will allow to bring inside the components of the protontherapy accelerator), armature of the attic between first basement and ground floor in the area reserved for TAE Life Sciences

January 2024

Overview of the expansion

On the left you can see the removable cover from which parts of the Hitachi accelerator will be lowered. On the right, on the other hand, construction of the boron therapy area continues, the slab between the first basement floor and the ground floor is being poured.

March 2025

Inauguration of the Expansion Project

Render of the new facility, exterior and interior; new HITACHI gantry for proton therapy; detail BNCT - TAE Life Sciences - TLS Alphabeam System

 

    Azienda con sistema di gestione per la Qualità Certificata
    Centre registered with QuESTIO, the mapping of players actively operating in the field of research and innovation
    Organization Accredited by Joint commision internatoional